Construction Update - 6/2/2010
Learning Commons Construction:
--Work on the front of the library continues: parking lot closed.
--Construction of Student Success Center at the back of library continues
--2nd floor renovation continues: use the back elevators or central stairwell for access to stacks.
"Projected" timeline:
June 21: Computer lab moves to back of 2nd floor
June 28: West side entrance to library opens; front entrance closes
July 1: Circulation Desk opens on 2nd floor
July 5: 2nd floor staff office construction begins (completion: Aug 16)
August 25: 1st floor renovation begins; Reference Desk and computers move to back of 3rd floor (completion: July 2011)
Other work in Perry Library:
--lights are being replaced throughout the library; to be completed June 30
--work on replacing the roof to begin soon