Construction Update 6/25
Learning Commons Construction:
-- The front library entrance is closed as of June 21. Users must enter through the east or west entrances.
-- The OCCS computer lab and mini learning commons are fully functional at the back of the 2nd floor. Access to the lab is from the back elevators.
-- 1st floor reference services and computers are available through early August, at which time they will be moved to the back of the 3rd floor.
- - - - ->Printing from these computers to the Reference printer is $.10/page. Printing to student accounts must be done in the 2nd floor lab.
-- Public workstations in the lobby will be unavailable as of August 1. Public accounts will no longer be available.
"Projected" timeline:
July 1: Circulation Desk opens on 2nd floor
July 5: 2nd floor staff office construction begins (completion: Aug 16)
August 1: 1st floor lobby cleared out; Public lobby computers shut down
early August: Reference Desk and computers move to back of 3rd floor (completion: July 2011)
August 25: 1st floor renovation begins to construct Learning Commons (completion: sometime at the end of 2011)
. . . . . . Construction of Student Success Center at the back of library continues