July 8th, 2010Learning Commons Construction:
-- Because of demolition at the west entrance to Perry Library, RAMP ACCESS is temporarily unavailable. Users needing ramp access are asked to use the east entrance.
-- 2nd floor MICROFORMS cabinets and equipment have moved to other locations on the 2nd floor:
* Microfilm cabinets are now located along the east exterior wall in call number order.
* Microfiche cabinets are located on the interior east wall.
* Reader/printers and video monitors are also located on the interior east wall. with
-- 4th floor JUVENILE BOOK collection and AUDIO-VISUAL materials (ranges 102-106) have been temporarily moved to the front area (west) of the 3rd floor (ranges 88-91) while a shift takes place on the 4th floor. Audio-visual materials will eventually be available at the 2nd floor circulation service desk in early August.
-----------------------------------------------------------------------------------------
"Projected" timeline:
July 5: 2nd floor staff office construction begins (completion: Aug 16)
August 1: 1st floor lobby cleared out; Public lobby computers and public accounts will be unavailable.
early August:
* Reference Desk and computers move to back of 3rd floor (through July 2011)
* Circulation Desk moves to 2nd floor
August 25: 1st floor renovation begins to construct Learning Commons (completion: sometime at the end of 2011)
. . . . . . Construction of Student Success Center at the back of library continues
. . . . . . Construction on the front of the library continues. Entrance to the library is from the east or west sides.
Reminder: Printing to student accounts must be done in the OCCS computer lab at the back of the 2nd floor. Access to the lab is from the back elevators.