Construction Update 8/13
Circulation Services Move from 1st to 2nd floor
The final walkthrough was done on the circulation offices and service areas. The office area was approved by everyone so the plan is still to move the circulation offices up on Monday or Tuesday next week. There are some issues with the other area so the circulation desk move will be delayed a few days.
Partitions erected on 1st-3rd floors
Temporary and permanent partitions are being constructed on the first, second and third floors. The partitions on the second and third floors are in anticipation of the third floor infill. The partitions on the first floor are in anticipation of the renovation work being done on first floor.
Reference Room Move from 1st to 3rd floor
The reference desk, public computers, and printers will be moving to the south side of third floor by August 25th. Wiring and cabling work is being done in advance of the move. The map alcove will be moved by the governments publications area.
Lobby 1st floor
The popular collection will be moved to second floor along with some of the lounge furniture. Other furniture will be either moved, surplused or stored.
North addition -- Front of library
The concrete has been poured and steel will be delivered the week of the 16th to 20th of August.
South addition -- Student Success Center
The steel has been completed and the concrete pour for the second floor has been completed.
Handicapped Ramp
The handicapped ramp on the west side of the library has been reopened and the railings have been installed.
Thank you for your continued patience during these developments!