Construction Update
In case you've been wondering... work continues as planned on the north and south additions to the Perry Library.
On the north addition -- Learning Commons:
-- finishing coats are being placed on the drywall partitions and soffits
-- the ceiling grid installation in the renovation/addition space is 2/3 complete
-- sprinkler work in the addition continues
-- other mechanical, electrical and plumbing installations continue and should be ready for inspection in May
-- roofing work will be completed in the next few weeks
-- work on the concrete patio for the café area has begun
-- fireproofing for the third floor infill continues
On the south addition -- Student Success Center:
-- BCOM( Bureau of Capital Outlay Management) inspection completed
-- paint, blinds and carpet on the 1st and 2nd floor rooms should be completed in two weeks
-- delivery and installation of doors should begin later this week
-- toilet partitions and accessories are being installed
-- fire alarm and air conditioning systems are being tested for startup
-- the water line to the building will soon be approved, with water available by 4/29
-- on the exterior, the courtyard has lights
Sometime in early Fall 2011, we will have two beautiful new spaces to serve ODU's students and faculty!!!